KISHTWAR, MARCH 02: The District Development Commissioner (DDC) Kishtwar, Dr Devansh Yadav today chaired a meeting of concerned officers to review physical and financial progress made under District Capex budget 2022-23 and to initiate action for the preparations of District Capex Budget 2023-24.
The DDC took a comprehensive review of the physical and financial achievements of the works being executed by different departments including Jal Shakti, PDD, PMGSY, PWD, RDD, Health and Education under various components of the District Capex budget in the district.
In the meeting, the chair was apprised that a total of 1823 number of works under UT Capex have been completed up to February 2023 and Rs 33 crore (Approx.) of fund has been utilized.
Moreover under Centrally Sponsored Schemes 32896 works have been completed by incurring the expenditure of 184.14 crores (approx.) so far, he was informed.
DDC on the occasion directed for cent percent completion of works and booking of expenditure before the end of the current financial year as the resumption of favourable weather is the best opportunity to complete the pending works.